Time-sensitive delivery of oversized medical equipment from China to Kazakhstan

Project cargo | Oversized handling | 20 days total
We organized a time-sensitive shipment of oversized medical equipment from China to Kazakhstan for a healthcare project. The key priority was safe handling and predictable delivery under a tight timeline, despite the holiday period and increased border congestion.
Route: China → Kazakhstan
Cargo: oversized, sensitive medical equipment (project cargo)
Constraints: tight delivery window, holiday-related border workload, zero tolerance for damage
Execution: project logistics planning, OOG documentation preparation, suitable equipment selection, and end-to-end coordination
Border milestone: clearance completed within 1 day despite congestion
Total duration: 20 days
The shipment was managed with a project-logistics approach: structured planning, documentation readiness for oversized cargo, and continuous coordination at each stage. This kept the move controlled and minimized risk at the most sensitive points — border procedures and cargo handling.
Result: delivered on time (slightly ahead of plan), with full cargo integrity and no incidents.